Westgold - Mt Henry Project
Project Description: -12mm Mill Feed
Commodity: Gold
Project Status: Current
Location: Norseman
Duration: 2 month
Project Parameters: 4 Stage Crushing Plant
Esperance Shire - Limestone Crushing Project
Project Description: Limestone Road Base
Commodity:Limestone
Project Status: Current
Location: Esperance
Duration: 3 years
Project Parameters: Single Stage Impactor Crushing & Screening
Project Description: -25mm Mill feed.
Commodity: Gold
Project Status: Current
Location: 45km South Leinster WA
Duration: 6 months contract.
Project Parameters: Min 40,000 ton per month
Notes: Hard Rock crushing contract using 3 stage crushing plant to supply supplementary mill feed to increase project tonnages.
Metals X - Blue Bird Project
Project Description: -12mm Mill feed.
Commodity: Gold
Project Status: Current
Location: Meekatharra
Duration: 14 months ongoing
Project Parameters: CSS 2 stage crushing plant.
Western Areas - Flying Fox
Project Description: Contract Crushing for Ore Sorting Australia
Commodity: Nickel Ore
Project Status: Complete
Location: Flying Fox Mine Site - Forrestania
Duration: 6 Months
Project Parameters: Crush and Screen 170,000 ton low grade Nickel Stockpile.
West Gold - Higginsville
Project Description: -12mm Emergency Mill feed
Commodity: Gold
Project Status: Completed May 2017
Location: Higginsville
Duration: 2 Months
Project Parameters: Mob Crush Screen 50,000 tons Emergency mill feed. Extremely Hard ore.
Notes: Less the two weeks from first Client contact to Producing mill feed onsite.
Central Norseman Gold Corporation LG Project
Project Description: Crushing and Screening low grade ore at various locations for CNGC Mill Operations at 100,000t per month run rate. Various size fractions and various ore types are treated on site
Commodity: Gold
Project Status: Completed July 2016
Location: Norseman
Duration: October 2014 - July 2016
Project Parameters: Monthly 100,000t mine, crush and screen and transporting to the Rom via Road Train.
Notes: CSS has been a complete service provider for this project by being the preferred materials handling Contractor. This project was moving out of trail basis this year into full capacity production and CSS has been appointed as the preferred materials handling Contractor.
OMYA Calcite Project
Project Description: Calcite separation from waste in OMYA Bathurst Quarry to upgrade quality of product delivered to the mill by using a mobile trommel. This needed to be done due to the amount offresh clay (Waste) in mined product.
Commodity: Calcite
Project Status: Complete
Location: Bathurst NSW
Duration: November 2015 till June 2016
Project Parameters: Monthly minimum 50 000t processed material per month.
Notes: This project commenced in November 2015 following on from trails carried out in Melbourne Victoria with this mobile trommel. OMYA Quarries had issues with feed stock material quality being presented which effected the final product. CSS as a solution based service provider put the concept forward utilising a mobile trommel to process and separate the waste. The initial trails have beensuccessful and it is envisaged that after a six month trial period, CSS will supply a bigger capacity unit on a contract basis to meet all the requirements for production and extend the quarry life by up to 10 years.
Golden Mile Milling Feed Crushing and Screen
Project Description: Complete Mill feed Crush and Screen project ROM Material processed to -20mm all in project.
Commodity: Gold
Project Status: Completed Mach 2016
Location: Kalgoorlie WA
Duration: November 2015 – July 2016mm
Project Parameters: Monthly 30,000t to 50,000t ROM Material crushed and screened to -20mm all in final product
Notes: This project equipment consists of a primary Screen, and a secondary cone closed circuit delivering a -20mm product at 210t/hr run rate, with the capacity to increase to 350tph if enough feed stock is delivered to the ROM.
Anglo-Ashanti Tropicana Emergency mill feed
Project Description: Screen primary material to -8mm final product due to front end of milling circuit undergoing unplanned maintenance
Commodity: Gold
Project Status: Completed
Location: Tropicana Gold, Goldfields WA
Duration: 16 Days from first contact
Project Parameters: 110 000t Screen to -8mmin 11 Days
Notes: This project showcased the alibility of CSS to be able to deliver a safe and professional turn key project in record time. From first contact by Anglo Gold, mobilisation of two 893 reclaimer screens, 4 loaders and 11 personnel, the completion of emergency mill feed took 16 Days, ensuring the client did not suffer any production down time through the Tropicana Mill. This project was completed without any safety concerns and to the highest standard.
Boral Quarries Deer Park
Project Status: Completed
Location: Deer Park, Melbourne Victoria
Duration: 3 Months May 2015 - August 2015
Project Parameters: Quarry waste rock screening operation (mine, screen and stockpile)
Notes: CSS Pty Ltd was contracted to process a minimum of 40,000t/month waste rock, with final product for Council tip cover. CSS was responsible for complete contract scope, mining, processing and stockpiling of material. Mobile trommel was utilised for this project due to the nature of feed material and wet conditions. Project was completed on time and above client expectation of volume and quantity of product.
Western Desert Roper Bar
Duration: 6 months January 2014 – June 2014
Commodity: Iron Ore
Project Parameters:Screen and Crush 240,000t/month Lump and Fines at 60% FE
Notes: CSS Pty Ltd was contacted by Peter Crooks, General Manager of Western Desert Resources in January 2014. Due to the onsite crushing contractor not performing and a dismal safety record, CSS mobilised Project Managers and Maintenance and Production teams to take over Crushing and Screening Project Management. Within 30 Days Production was increased by 60% and no LTI reported, after all logistics and management and safety systems were Implemented. This site was handed back to owner operator at the end of June 2014.
Hope Downs 4 Rio Tinto
Project description: Project Management and Equipment Supply including Operations and Maintenance
Duration: 14 Months Dec 2013 – January 2014
Commodity: Iron Ore
Project Parameters: Crush Screen and Haul 340,000t/month lump and Fines FE
Notes: CSS Pty Ltd completed this project sitting under another contractor’s banner project parameters, complete project management equipment hire maintenance and operational support. CSS personnel setup and executed the initial 1.8mt 6-month project professionally and on time to a strict rail and shipment schedule resulting in an 8-month project extension .
Frances Creek Iron Ore project
Project description: Complete crushing and screening site processing in JV with Barminco
Duration: January 2010 till January 2015
Project Parameters: Screen and Crush 200,000t/month Lump and Fines Iron ore, services consisted of project Management, equipment hire and complete circuit maintenance, CSS was contracted to operate and maintain site wet plant as well for a period of 6 months during initial start-up.
Notes: CSS Pty Ltd was contracted by Barminco at the start of the project, to turn a loss making project around where none of the project parameters had been met, over a period of 3 months the CSS team mobilised to site and restarted the project allowing Barminco to receive a 1 year project extension after the initial contract, when the Barminco Crushing and Screening contract finished, CSS in conjunction with the Owner operator project managed, and hired equipment to successfully run the Iron Ore operation till end of life in January 2015.
BHP Yandi 10MTPA
Project description: 10MTPA 5 mobile crushing plant operation
Duration: 3 Years
Project Parameters: Complete Project management on behalf of HWE Miningfor BHP Billiton Iron Ore
Notes: Involved with Setup and execution of 10MTPA project, this included 5 crushing circuits producing -12mm final product, 72 project team was involved, from operators, maintenance personnel, and planners etc.
CONTACT
Services